07 The laydown yard · for the technical manager
The detail for the person who has to stand behind the report.
You approve the scope, and you can say no. This sheet states what Bolting Inspection assists with, what your special inspector controls and what stays true on every project.
Who does what
The AI checks and drafts. The special inspector finds and signs.
| Question | Answer |
|---|---|
| Does the AI inspect or sign? | No. It checks what the camera sees and drafts the record. The special inspector makes every finding and signs every report. |
| What does the report show? | Three sources, kept apart: what the inspector witnessed, what the AI observed and what the contractor supplied. |
| What does it cover? | It assists with every task the special inspector is required to perform, before, during and after bolting. On each bolted connection it checks the bolts, their markings and the match marks. |
| What evidence goes into the report? | Enhanced visual evidence for every item, whether it passes or has a deficiency. That goes beyond what is required. |
| What happens when it cannot see something? | It says so and asks for another view. A check without enough evidence stays open. Nothing passes on a guess. |
| How is bolt pretension established? | By the installation method, which the special inspector verifies. Bolting Inspection does not measure or judge bolt pretension from a photo. |
| How is a deficiency recorded? | Each deficiency cites the detail and the drawing revision, with the photo behind it, and goes to the erector for corrective action. |
| Will the building official and the engineer of record accept the reports? | Nothing they require changes. The same approved agency performs the same required special inspections and issues reports in its own format. |
Every required task
It assists with everything the special inspector is required to do.
The inspection tasks are the ones your project sets out, organized as AISC 360 Chapter N organizes them: before, during and after bolting. The special inspector performs each one.
| Stage | What the special inspector is required to do | How Bolting Inspection assists |
|---|---|---|
| Before bolting | Manufacturer certifications. Fastener markings. The correct fastener and procedure for the joint detail. Faying surface and hole condition. Pre-installation verification. Fastener storage. | Reads keg labels and fastener markings, matches each lot to its manufacturer certification and pre-installation verification record, and flags a lot with no record. |
| During bolting | Fastener assemblies in all holes, with washers and nuts positioned. Snug-tight condition before pretensioning. The element not turned by the wrench held from rotating. Tightening that progresses from the most rigid point. | Takes what the inspector witnesses by voice, with the time and the place, and prompts for any task in the day’s scope not yet covered. |
| After bolting | Acceptance or rejection documented for each bolted connection. Deficiencies issued and closed. | Guides a sweep of every bolt, records the inspector’s finding, sends each deficiency to the erector and tracks corrective action through reinspection. |
| Reporting | Daily field reports. Deficiency notices. The Final Report of Special Inspections. | Drafts each report from the record, in your format, for the special inspector to review and sign. |
| Evidence | A record of what was inspected and what was found. | Adds enhanced visual evidence for every item, whether it passes or has a deficiency. That goes beyond what is required. |
The project’s Statement of Special Inspections and approved documents set the scope, in the code edition the project cites. The first release covers these tasks for turn-of-nut and snug-tightened joints.
First release
What it covers at launch.
| Item | First release |
|---|---|
| Bolting work covered | Turn-of-nut and snug-tightened joints. |
| Inspection tasks | Before, during and after bolting, as your Statement of Special Inspections sets them out. |
| Later release | Twist-off tension control bolts and direct tension indicators. |
| Records kept with the work | Inspector certifications and calibration records. |
| Device | iPhone 15 Pro and later. Nothing new to wear or carry. |
| With no signal | Photos, video, dictation and signing work. In the first release the AI analysis runs in the cloud when the phone reconnects. Analysis on the phone follows in the next release. |
| Reports | Your own template, as PDF and data. Connections to agency and contractor systems are planned. |
| Site security | Recording is limited to the inspection. Faces are blurred, restricted areas are blocked and every access is logged. Cloud analysis of site images needs the owner’s approval on each project. |
The pilot targets
Agreed in advance. Measured on your steel package.
| Measure | Pilot target |
|---|---|
| Report and review time | At least 20% less |
| Report errors | No increase |
| Critical deficiencies passed in error | None, in release evaluation |
These are targets for the pilot. They are not measured results, and none is promised. The pilot runs beside your current process, so your existing reports remain the record.
What stays true on every project
What you can hold us to.
- The special inspector decides. The AI checks what the camera sees and drafts the record. Every finding and every signature is the inspector’s.
- Pretension comes from the method. The special inspector verifies the installation method on the steel. Bolting Inspection does not measure bolt pretension from an image.
- Open until seen. When it cannot see enough, it says so and asks for another view. That check stays open.
- Your scope and your format stay. The Statement of Special Inspections stays as it is, and reports go out in your own format.
- Targets are labeled as targets. No pilot has been measured yet, so every figure about the product is a pilot target.
Figures are pilot targets, not measured results. The special inspector makes every finding and signs. Capabilities are subject to field validation and project acceptance.